propertylist

PA/00679/22: sanction in San Pawl il-Bahar

Site at, Triq Busewdien, Wardija, San Pawl il-Bahar

To sanction; (1) areas of deposited soil onto existing fields, (2) removal of previously constructed pillars to form gate as mentioned in EC00102/07 and EC00459/10, (3) planting of various types of trees, (4) timber gate, (5) works on rubble walls. Proposed (a) construction of pump room with underground reservoir, (b) maintenance works to the existing rubble walls (c) planting of endemic trees replacing eucalyptus trees.

Status
Status being checked
Location
Site at, Triq Busewdien, Wardija, San Pawl il-Bahar
Locality
San Pawl il-Bahar
Applicant
Mr Paul Zahra Jr.
Perit
Dr Edwin Mintoff
Type of works
Sanctioning

Case details on the Planning Authority website

Plans, case officer report and decision on eapps

Planning activity around Site at, Triq Busewdien, Wardija, San Pawl il-Bahar

17 other applications within 300 m: 7 granted, 0 refused, 4 pending. 100% of decided applications nearby were granted. Tallest granted nearby: 2 floors (PA/03099/23).

On Triq Busewdien: 15 other applications, 7 granted and 0 refused; granted buildings are typically 2 floors, the tallest 2. Periti active on this street: X,Y,Z Architecture & Design, Edwin Mintoff, Reuben Cauchi.

Approval estimate for sanctioning applications like this here: about 95% (likely range 65–100%, low reliability, from 1 comparable decision nearby). Indicative only. It's based on decisions for similar nearby applications, not on the drawings or the case officer's report; it gets better as documents are added from eapps.