PA/00941/26: Following outline development permission PA/04377/24 in Qormi

Site at, Tal-Handaq, Triq tal-Handaq, Sqaq iz-Ziemel, Qormi

Following outline development permission PA/04377/24, proposed demolition of existing boundary walls and single-storey structure, proposed excavation of site to include two basement levels and a water reservoir, and proposed construction of 4 above-ground levels to include a Class 6A warehouse with an ancillary parking facility and an office space. In view of the change of alignment, the application includes the construction of a public footpath and the formation and asphalting of the road surface within the site boundary.

Status
Granted (This application has been approved by Planning Board / Commission.)
Location
Site at, Tal-Handaq, Triq tal-Handaq, Sqaq iz-Ziemel, Qormi
Locality
Qormi
Applicant
Misrah Kola 2020 Limited Attn: Dorianne Tabone
Perit
Perit Mark Arrigo
Application type
Full development permission
Zone
Outside Development Zone
Type of works
Demolition & New Construction (Commercial)
Height
4 floors
Received
19 December 2025
Validated
18 February 2026
Published
18 February 2026
Comments close
20 March 2026
Recommendation
Refuse Permission
Decision
Grant Permission
Decision date
5 August 2026
Permit expires
19 August 2031

Case details on the Planning Authority website

Plans, case officer report and decision on eapps

Planning activity around Site at, Tal-Handaq, Triq tal-Handaq, Sqaq iz-Ziemel, Qormi

112 other applications within 300 m: 71 granted, 3 refused, 10 pending. 96% of decided applications nearby were granted. Tallest granted nearby: 5 floors (PA/05912/25).

On Triq tal-Handaq: 35 other applications, 21 granted and 0 refused; granted buildings are typically 3 floors, the tallest 4. Periti active on this street: George Farrugia, JBA Periti, Robert Grech, Samuel Formosa, Christian Spiteri.

Approval estimate for demolition & new construction applications like this here: about 95% (likely range 65–100%, low reliability, from 19 comparable decisions nearby). Outside the development zone, where approvals are harder. Indicative only. It's based on decisions for similar nearby applications, not on the drawings or the case officer's report; it gets better as documents are added from eapps.

More by Mark Arrigo

All applications by Mark Arrigo

More from Misrah Kola 2020 Ltd

All planning applications in Qormi