PA/01440/24: demolish the site in preparation for future in St Julians
Qube, Triq Santa Rita, Paceville, San Giljan
To demolish the site in preparation for future development.
- Status
- Granted (This application has been approved by Planning Board / Commission.)
- Location
- Qube, Triq Santa Rita, Paceville, San Giljan
- Locality
- St Julians
- Applicant
- EDR Co Ltd Attn: Dorian Dalli
- Perit
- Perit Sean Buttigieg
- Application type
- Full development permission
- Zone
- Within Development Zone
- Type of works
- Demolition & New Construction
- Received
- 15 November 2023
- Validated
- 13 March 2024
- Published
- 13 March 2024
- Comments close
- 19 April 2024
- Recommendation
- Grant Permission
- Decision
- Grant Permission
- Decision date
- 24 October 2024
- Permit expires
- 4 December 2029
Case details on the Planning Authority website
Plans, case officer report and decision on eapps
Planning activity around Qube, Triq Santa Rita, Paceville, San Giljan
3 other applications on the same street: 1 granted, 0 refused, 2 pending.
On Triq Santa Rita: 3 other applications, 1 granted and 0 refused. Periti active on this street: Sean Buttigieg.
Approval estimate for demolition & new construction applications like this here: about 95% (likely range 65–100%, low reliability, from 0 comparable decisions nearby). Indicative only. It's based on decisions for similar nearby applications, not on the drawings or the case officer's report; it gets better as documents are added from eapps.
- PA/03993/26 St Julians: To propose minor internal alterations and change of use from Class 4D to Class 3C.
- PA/06402/25 St Julians: Sanctioning of part change of use from offices to Class 4C and minor alterations on all floors: Alterations include relocation of vertical access, the…
- PA/05212/24 St Julians: To demolish existing bar and excavate site to construct a Class 3B, bed and breakfast hotel; underlying Class 4C and Class 4D outlets ancillary to hotel…
More by Sean Buttigieg
- PA/07763/26 Ghaxaq: Sanctioning of minor variations from last approved PB/04162/79. Variations include: addition of an aperture overlooking the backyard in the stairwell leading…
- PA/06943/26 San Pawl il-Bahar: Sanctioning of minor variations from last approved PA/4740/19. Variations include location of walls, internal height and location and width of apertures.…
- PA/06889/26 Birkirkara: Sanctioning of minor variations from the last approved PA/9351/19, including minor changes to the location of internal partitions and apertures, minor…
- PA/06439/26 Gzira: Reversion of the property's use class to a pre-1968 residence, conversion of the domestic garage approved under PA/4784/06 into an open-plan studio flat on a…
- PA/06105/26 Msida: Sanctioning of minor variations from last approved PA/05269/06. Variations include: position of apartment, not on plan, but in section. The size and presence…
- PA/05964/26 San Pawl il-Bahar: Sanctioning of minor variations from the latest approved permit PA/5501/25. Variations include changes to the location of internal partitions and the…
All applications by Sean Buttigieg
More from EDR Co Ltd
- PA/06870/25 Zabbar: To demolish existing, and propose 6 garages at basement level, Class 4B shop and 2 maisonettes at ground floor, 9 apartments at first, second and third, and…
- PA/06402/25 St Julians: Sanctioning of part change of use from offices to Class 4C and minor alterations on all floors: Alterations include relocation of vertical access, the…
- PA/02203/25 Xghajra: To demolish approved roof structures (PA 6646/01) and build 5 overlying apartments at level 3 and 5 receded units at receded floor level, works to include the…
- PA/01869/25 Mellieha: To demolish existing terraced house, excavate and build a basement garage (6 parking spaces), 1 overlying maisonette, 3 apartments and a receded floor.
- PA/05212/24 St Julians: To demolish existing bar and excavate site to construct a Class 3B, bed and breakfast hotel; underlying Class 4C and Class 4D outlets ancillary to hotel…
- PA/04633/24 Birkirkara: Demolition of existing terraced house, construction of basement garages, proposed Class 4A office at ground floor, six apartments and penthouse at recessed…