PA/02912/24: sanction Class 4B as built including placing in San Pawl il-Bahar
Eurosaver Supermarket, Triq Censu Tanti, Bugibba, San Pawl il-Bahar
To sanction Class 4B as built including placing of services in the backyard, new cold store in the backyard, lightweight canopy in backyard, shifting of partition wall location, external alterations to parapet wall, LED screen in façade, signs covering roller shutters, new sign covering roller shutter above the store entrance, placing of trolleys in front garden during operational hours only and location of BCRS machine and ATM. Application also includes change of use from garage to stores interconnected to the Class 4B.
- Status
- Refused (Planning Authority decision reviewed by Appeals Board / EPRT)
- Location
- Eurosaver Supermarket, Triq Censu Tanti, Bugibba, San Pawl il-Bahar
- Locality
- San Pawl il-Bahar
- Applicant
- Mario Bolous
- Perit
- Perit Stanley Cortis
- Application type
- Full development permission
- Zone
- Within Development Zone
- Type of works
- Sanctioning
- Received
- 5 November 2023
- Validated
- 10 July 2024
- Published
- 10 July 2024
- Comments close
- 26 August 2024
- Recommendation
- Refuse Permission
- Decision
- Refuse Permission
- Decision date
- 15 October 2025
Case details on the Planning Authority website
Plans, case officer report and decision on eapps
Planning activity around Eurosaver Supermarket, Triq Censu Tanti, Bugibba, San Pawl il-Bahar
173 other applications within 300 m: 102 granted, 5 refused, 20 pending. 95% of decided applications nearby were granted. Tallest granted nearby: 8 floors (PA/08467/24).
On Triq Censu Tanti: 9 other applications, 6 granted and 0 refused; granted buildings are typically 6 floors, the tallest 8. Periti active on this street: George Farrugia.
Approval estimate for sanctioning applications like this here: about 95% (likely range 65–100%, medium reliability, from 46 comparable decisions nearby). Indicative only. It's based on decisions for similar nearby applications, not on the drawings or the case officer's report; it gets better as documents are added from eapps.
- PA/00068/22 San Pawl il-Bahar: Demolition of the existing structure, construction of two basement levels including 34 garages and 2 parking spaces. Construction of 5 maisonettes (2 no.…
- PA/00975/24 San Pawl il-Bahar: Internal and external alterations to approved permit PA68/22, removing a duplex apartment on the fifth floor, internal and external alterations to all floors,…
- PA/00161/25 San Pawl il-Bahar: Construction of 3 levels of basement with 77 closed garages and 8 parking spaces, with overlying ground floor with 7 Class 4B units, 6 floors with 8…
- PA/08467/24 San Pawl il-Bahar: Construction of a Class 3B 3-star hotel, consisting of a ground floor comprising in lounge, bar, breakfast area, luggage room, 7 overlying floors and 2…
- PA/06272/23 San Pawl il-Bahar: Full demolitions of existing building and excavation of 4 levels basement in preparation for multipurpose use building.
- PA/00135/25 San Pawl il-Bahar: To sanction property as constructed from PB/03863/79.
- PA/02326/26 San Pawl il-Bahar: Sanctioning of supermarket from ground floor level to basement floor level. Application includes change of use to recreational leisure facilities (Class 3C)…
- PA/04768/26 San Pawl il-Bahar: Alterations to first floor maisonette including demolition, construction of overlying 5 apartments with overlying penthouse.
- PA/04064/25 San Pawl il-Bahar: Sanctioning of minor internal alterations and correction of pool dimensions.
- PA/06806/24 San Pawl il-Bahar: To demolish existing block of apartments. Excavation and construction of basement level. Construction of 3 maisonettes at ground floor level, 18 apartments…
- PA/01096/22 San Pawl il-Bahar: To sanction variations from approved PA2699/20 including internal alterations and proposed construction of wall and installation of aluminium gate in front…
- PA/03093/22 San Pawl il-Bahar: Proposed change of use of part of garage used for the parking of private vehicles into Class 4B including an area for butcher and retain part of garage for…
- PA/05851/24 San Pawl il-Bahar: To demolish existing first floor apartment, carryout extensions at ground floor level (adding external areas only) and construct 5 overlying apartments and…
- PA/07113/26 San Pawl il-Bahar: To sanction garage as existing from approved PA4359/81, to change use from garage to Class 4B and to propose installation of sign and internal partition walls.
- PA/04754/26 San Pawl il-Bahar: Demolition of existing building and construction of 2 no. garages at ground floor level and 2 no. apartments at first and second floor levels.
More by Stanley Cortis
- PA/06716/26 Senglea (Isla): Proposed minor external and internal alterations including railing at roof level and jacuzzi to an existing rehabilitated palazzino located within a UCA in…
- PA/06451/26 Birkirkara: To sanction internal and external alterations to apartment at third floor as built from PA10399/17.
- PA/06428/26 Fgura: Demolition of the existing stairwell at third-floor level and the construction of two separate duplex residential units at third-floor and receded…
- PA/06280/26 Zurrieq: Alterations to existing terraced house to convert the first floor into an apartment and extension at roof level in order to construct two other residential…
- PA/05204/26 Naxxar: Proposed multi-lane slide as part of the slide group including splash pool and underlying relating facilities.
- PA/03229/26 Marsaxlokk: To sanction underground reservoir as built and proposed construction of gate and maintenance/increase in height of rubble wall.
All applications by Stanley Cortis
More from Mario Bolous
- PA/06288/25 San Pawl il-Bahar: Change of use from existing garage (to sanction) and souvenir shop (covered by trading license) into Class 4B barber integrated with Class 4C outlet and a…
- PA/03093/22 San Pawl il-Bahar: Proposed change of use of part of garage used for the parking of private vehicles into Class 4B including an area for butcher and retain part of garage for…