> Granted planning application in Sliema: Proposed excavation of site and construction of parking for private use at basement, 1 Class 4A office and 1…

Planning applications › Sliema › PA0295023

# PA/02950/23: excavation of site and construction of parking in Sliema

29, Triq il-Madonna Tas-Sacro Cuor c/w, Ix-Xatt, Sliema

Proposed excavation of site and construction of parking for private use at basement, 1 Class 4A office and 1 maisonette at ground floor, 18 apartments and 2 penthouses within the same approved building height and re design of facade, in lieu of PA7807/17 renewed by PA5757/22.

- **Status:** Granted (This application has been approved by Planning Board / Commission.)
- **Location:** 29, Triq il-Madonna Tas-Sacro Cuor c/w, Ix-Xatt, Sliema
- **Locality:** [Sliema](https://propertylist.mt/planning-applications/sliema)
- **Applicant:** [Fran Schembri](https://propertylist.mt/applicant/fran-schembri)
- **Perit:** [JG Periti](https://propertylist.mt/perit/jg-periti)
- **Application type:** Full development permission
- **Zone:** Within Development Zone
- **Type of works:** New Construction (Residential)
- **Residential units:** 21
- **Received:** 13 March 2023
- **Validated:** 24 May 2023
- **Published:** 20 September 2023
- **Comments close:** 20 October 2023
- **Recommendation:** Refuse Permission
- **Decision:** Grant Permission
- **Decision date:** 10 January 2024
- **Permit expires:** 24 January 2029

[Case details on the Planning Authority website](https://www.pa.org.mt/pacasedetails?CaseType=PA/02950/23)

[Plans, case officer report and decision on eapps](https://eapps.pa.org.mt/Case/CaseDetails?caseType=PA&casenumber=02950&caseYear=23)

## Planning activity around 29, Triq il-Madonna Tas-Sacro Cuor c/w, Ix-Xatt, Sliema

140 other applications within 300 m: 88 granted, 6 refused, 16 pending. 94% of decided applications nearby were granted. Tallest granted nearby: 10 floors (PA/04549/21).

On Triq il-Madonna Tas-Sacro Cuor: 1 other application, 1 granted and 0 refused.

Approval estimate for new construction applications like this here: about 95% (likely range 65–100%, low reliability, from 11 comparable decisions nearby). Indicative only. It's based on decisions for similar nearby applications, not on the drawings or the case officer's report; it gets better as documents are added from eapps.

- [**PA/07139/26** Sliema](https://propertylist.mt/permit/PA-07139-26/sliema-sanction-property-as-built): To sanction property as built. To propose change of use from a private garage to Class 4B. To carry out internal and external changes and to fix a sign. Pending, validated 14 October 2026, 9 m away
- [**PA/02370/26** Sliema](https://propertylist.mt/permit/PA-02370-26/sliema-addition-of-one-parking-space-in-basement): Addition of one parking space in basement levels as approved in PA/07944/22; sanctioning of lock-up garages as constructed, removal of door jambs in two… Granted, validated 15 April 2026, 23 m away
- [**PA/03851/25** Sliema](https://propertylist.mt/permit/PA-03851-25/sliema-change-to-shift-facade-fascia-line): Proposed change to shift facade fascia line. Granted, validated 6 August 2025, 23 m away
- [**PA/02433/25** Sliema](https://propertylist.mt/permit/PA-02433-25/sliema-layout-in-lieu-of-those-approved-in): Proposed layout in lieu of those approved in PA/07944/22, mainly consisting in the construction of two plunge pools on the roofs of each of the two penthouses. Granted, validated 19 May 2025, 23 m away
- [**PA/04213/23** Sliema](https://propertylist.mt/permit/PA-04213-23/sliema-construct-extension-to-existing-apartment-at-fifth): To construct extension to existing apartment at fifth floor level and to construct a receded 1 bedroom apartment at sixth floor level. Granted, validated 12 July 2023, 6 floors, 24 m away
- [**PA/01275/23** Sliema](https://propertylist.mt/permit/PA-01275-23/sliema-retention-of-existing-facade): Retention of existing facade, relocation of staircase, reusing of some roof elements and demolition of remaining internal structure. Construction of 1… Granted, validated 8 March 2023, 24 m away
- [**PA/05865/23** Sliema](https://propertylist.mt/permit/PA-05865-23/sliema-sanction-as-built-basement-levels): To sanction as built basement levels, with a layout different to that approved in PA9680/19, including removal of ramp and interconnection with adjacent… Granted, validated 22 November 2023, 27 m away
- [**PA/00601/24** Sliema](https://propertylist.mt/permit/PA-00601-24/sliema-sanction-variations-to-approved-permit-pa03494-16): To sanction variations to approved permit PA03494/16; reducing pedestrian access to 1.50m. Granted, validated 7 February 2024, 28 m away
- [**PA/01565/23** Sliema](https://propertylist.mt/permit/PA-01565-23/sliema-sanction-alterations-to-apartment-approved-in-pa3225-00): To sanction alterations to apartment approved in PA3225/00. Granted, validated 25 May 2023, 30 m away
- [**PA/01824/25** Sliema](https://propertylist.mt/permit/PA-01824-25/sliema-construction-of-2-pools-at-roof-level): Proposed construction of 2 pools at roof level, approved by PA2950/23. Granted, validated 18 March 2025, 31 m away
- [**PA/01798/25** Sliema](https://propertylist.mt/permit/PA-01798-25/sliema-changes-to-pa1741-23-to-sanction-minor-internal): Changes to PA1741/23 to sanction minor internal alterations, removal of internal staircase to create a separate 1 bedroom apartment (no structural works). Granted, validated 23 April 2025, 36 m away
- [**PA/01741/23** Sliema](https://propertylist.mt/permit/PA-01741-23/sliema-renewal-of-pa10295-17-for-the-proposed-extension): Renewal of PA10295/17 for the proposed extension of existing residential unit including construction of an additional receded floor level and conversion of… Granted, validated 2 May 2023, 37 m away
- [**PA/02601/24** Sliema](https://propertylist.mt/permit/PA-02601-24/sliema-demolish-a-hotel-and-underlying-commercial-premises): To demolish a hotel and underlying commercial premises, to excavate site (including that covered by PA6894/20) and carry out alterations to existing apartment… Granted, validated 28 August 2024, 40 m away
- [**PA/05954/23** Sliema](https://propertylist.mt/permit/PA-05954-23/sliema-renewal-to-pa7813-18): Renewal to PA7813/18 (Proposed demolition of existing and construction of Class 3A guesthouse). Granted, validated 14 February 2024, 42 m away
- [**PA/03750/24** Sliema](https://propertylist.mt/permit/PA-03750-24/sliema-demolish-the-remaining-building): To demolish the remaining building (approved in PA 6894/20 and excavate accordingly).(as interim to ongoing full permit PA2601/24 covering the entire site… Granted, validated 26 June 2024, 44 m away

## More by JG Periti

- [**PA/07460/26** San Pawl il-Bahar](https://propertylist.mt/permit/PA-07460-26/san-pawl-il-bahar-renewal-of-pa-977-14-demolition-of-existing-bank): Renewal of PA/977/14- Demolition of existing bank and erect same including basement parking and contingency building. Pending, validated 28 October 2026
- [**PA/07376/26** Rabat](https://propertylist.mt/permit/PA-07376-26/rabat-partial-excavation-of-site): Proposed partial excavation of site, while retaining and preserving the rest of the site due to the presence of high value archeological features, and… Pending, validated 28 October 2026
- [**PA/07328/26** San Pawl il-Bahar](https://propertylist.mt/permit/PA-07328-26/san-pawl-il-bahar-construction-of-pump-chamber): Proposed construction of pump chamber. Pending, validated 21 October 2026
- [**PA/07217/26** Swieqi](https://propertylist.mt/permit/PA-07217-26/swieqi-relocation-of-public-service-garage-space): Relocation of public service garage space, addition of pool at roof level, reconfiguration of reservoirs and other changes. Pending, validated 21 October 2026
- [**PA/06980/26** Tarxien](https://propertylist.mt/permit/PA-06980-26/tarxien-demolition-of-existing-dwellings): Proposed demolition of existing dwellings, removal of material, excavation, and construction of 6 basement garages, 2 maisonettes, 6 apartments and 1 penthouse. Pending, validated 14 October 2026, 3 floors plus a receded floor
- [**PA/06947/26** Iklin](https://propertylist.mt/permit/PA-06947-26/iklin-sanctioning-of-clearance-of-site-and-excavation): Sanctioning of clearance of site and excavation. Proposed open storage and construction of 2 floors of warehousing Class 6A at lower basement, basement and… Pending, validated 7 October 2026, 1 floor

[All applications by JG Periti](https://propertylist.mt/perit/jg-periti)

## More from Fran Schembri

- [**PA/04420/26** Mosta](https://propertylist.mt/permit/PA-04420-26/mosta-variations-from-already-approved-pa6307-22): Proposed variations from already approved PA6307/22. Variations include internal and external layout, part alterations and change of use at 1st and 2nd floor… Pending, validated 1 July 2026
- [**PA/01890/26** Birkirkara](https://propertylist.mt/permit/PA-01890-26/birkirkara-clearing-of-site-and-excavation): Proposed clearing of site and excavation, construction of reservoir and generator room and overlaying carwash and valeting area. Pending, validated 25 March 2026, 1 floor
- [**PA/04295/25** Gzira](https://propertylist.mt/permit/PA-04295-25/gzira-demolition-of-existing-building): Proposed demolition of existing building, excavation of site and construction of reservoir, 35 garages and substation at basement levels. Class 4B retail at… Granted, validated 2 July 2025, 6 floors
- [**PA/03926/25** Pieta](https://propertylist.mt/permit/PA-03926-25/pieta-demolition-of-existing-dwellings): Proposed demolition of existing dwellings, excavation and construction of 55 basement garages, 10 maisonettes, 73 apartments, 9 penthouses. Application also… Suspended, validated 24 June 2026, 5 floors plus a receded floor
- [**PA/03239/25** Mosta](https://propertylist.mt/permit/PA-03239-25/mosta-demolition-of-existing-dwelling): Proposed demolition of existing dwelling, excavation of site, construction of 3 basement garages, maisonette at ground floor, overlying 3 apartments and 1… Granted, validated 21 May 2025, 1 floor plus a receded floor
- [**PA/02834/25** Attard](https://propertylist.mt/permit/PA-02834-25/attard-clearing-of-site-and-excavation-and-construction): Proposed clearing of site and excavation and construction of reservoir and generator room, overlying car-wash, including signage and alterations to boundary… Pending, validated 7 May 2025

[All planning applications in Sliema](https://propertylist.mt/planning-applications/sliema)