PA/07548/23: changes from approved permit PA/06459/19 in Hamrun
1,2,3,4,5,6,7, Triq Antonio Miruzzi, Santa Venera & Site at, Triq Joseph Abela Scolaro, Hamrun
Proposed changes from approved permit PA/06459/19, including the introduction of basement level -3, internal changes, changes to facade design, and proposed construction of pools at roof levels. This new application will now include 89 garages, 58 residential and 4 commercial Class 4B shops.
- Status
- Granted (This application has been approved by Planning Board / Commission.)
- Location
- 1,2,3,4,5,6,7, Triq Antonio Miruzzi, Santa Venera & Site at, Triq Joseph Abela Scolaro, Hamrun
- Locality
- Hamrun
- Applicant
- Portland Properties Limited Att. Malcolm Mallia
- Perit
- JG Periti
- Application type
- Full development permission
- Zone
- Within Development Zone
- Type of works
- New Construction (Residential)
- Residential units
- 58
- Received
- 3 October 2023
- Validated
- 20 December 2023
- Published
- 20 December 2023
- Comments close
- 29 January 2024
- Recommendation
- Refuse Permission
- Decision
- Grant Permission
- Decision date
- 14 January 2025
- Permit expires
- 29 January 2030
Case details on the Planning Authority website
Plans, case officer report and decision on eapps
Planning activity around 1,2,3,4,5,6,7, Triq Antonio Miruzzi, Santa Venera & Site at, Triq Joseph Abela Scolaro, Hamrun
130 other applications within 300 m: 87 granted, 3 refused, 10 pending. 97% of decided applications nearby were granted. Tallest granted nearby: 6 floors (PA/08123/24).
On Triq Antonio Miruzzi: 2 other applications, 2 granted and 0 refused; granted buildings are typically 4 floors, the tallest 4.
Approval estimate for new construction applications like this here: about 95% (likely range 65–100%, low reliability, from 14 comparable decisions nearby). Indicative only. It's based on decisions for similar nearby applications, not on the drawings or the case officer's report; it gets better as documents are added from eapps.
- PA/04986/23 Santa Venera: To sanction changes to private car garage approved in PB 4024/ 85 and propose change of use to Class 4B Green Grocer and store. Changes being sanctioned…
- PA/04337/25 Hamrun: To sanction existing garage as built and proposed change of use from garage to public service garage.
- PA/06596/25 Santa Venera: Demolition of existing maisonette at first floor, construction of common parts at ground floor and including excavation of lift pit, construction of three x3…
- PA/07263/25 Santa Venera: Sanctioning of garage as built and change of use from garage to public service garage.
- PA/00659/20 Santa Venera: Conversion of window to door on facade
- PA/02527/26 Hamrun: Proposed demolition of dangerous garage, removal of fill material up to rock level (as required for structural purposes), and reconstruction of garage.
- PA/02526/26 Hamrun: Proposed demolition and reconstruction of residence.
- PA/02700/26 Hamrun: Proposed clearing of site from debris following collapse, removal of fill material up to rock level (as required for structural purposes), and construction of…
- PA/02355/25 Santa Venera: Demolition of existing warehouse already approved by DS/427/24. Proposed building of street level garages and warehousing Class 6A, and proposed residential…
- PA/00576/25 Hamrun: Change of use of domestic garage as per approved PA/03365/14 to a public service garage.
- PA/00356/26 Santa Venera: Temporary change of use for a period of one year from class 6a General Warehousing to a public service garage at part basement level (level - 4).
- PA/08588/24 Hamrun: Sanctioning of garage as built (variations from PA3365/14). Removal of cross ventilation (as a result of roofing over shaft by third parties) and alterations…
- PA/06806/23 Santa Venera: Replacement of front door to an existing pre-1967 property.
- PA/04712/25 Santa Venera: To sanction changes from approved permits PA/04388/24. Furthermore, the amendment consists of shifting of wall from original permit PA/05272/06.
- PA/02769/24 Santa Venera: Proposed public service garage at roof level. No construction works involved.
More by JG Periti
- PA/07460/26 San Pawl il-Bahar: Renewal of PA/977/14- Demolition of existing bank and erect same including basement parking and contingency building.
- PA/07376/26 Rabat: Proposed partial excavation of site, while retaining and preserving the rest of the site due to the presence of high value archeological features, and…
- PA/07328/26 San Pawl il-Bahar: Proposed construction of pump chamber.
- PA/07217/26 Swieqi: Relocation of public service garage space, addition of pool at roof level, reconfiguration of reservoirs and other changes.
- PA/06980/26 Tarxien: Proposed demolition of existing dwellings, removal of material, excavation, and construction of 6 basement garages, 2 maisonettes, 6 apartments and 1 penthouse.
- PA/06947/26 Iklin: Sanctioning of clearance of site and excavation. Proposed open storage and construction of 2 floors of warehousing Class 6A at lower basement, basement and…