> Granted planning application in San Pawl il-Bahar: Proposed construction of greenhouses and ancillary reservoir. Perit Julian Borg. Validated 6 November 2024.

Planning applications › San Pawl il-Bahar › PA0755224

# PA/07552/24: construction of greenhouses and ancillary reservoir in San Pawl il-Bahar

Site at (Field), Gebel Sarnu, San Pawl il-Bahar

Proposed construction of greenhouses and ancillary reservoir.

- **Status:** Granted (This application has been approved by Planning Board / Commission.)
- **Location:** Site at (Field), Gebel Sarnu, San Pawl il-Bahar
- **Locality:** [San Pawl il-Bahar](https://propertylist.mt/planning-applications/san-pawl-il-bahar)
- **Applicant:** Andrew & Joan Vella
- **Perit:** [Perit Julian Borg](https://propertylist.mt/perit/julian-borg)
- **Application type:** Full development permission
- **Zone:** Outside Development Zone
- **Type of works:** New Construction
- **Received:** 26 August 2024
- **Validated:** 6 November 2024
- **Published:** 6 November 2024
- **Comments close:** 6 December 2024
- **Recommendation:** Refuse Permission
- **Decision:** Grant Permission
- **Decision date:** 1 July 2025
- **Permit expires:** 6 August 2030

[Case details on the Planning Authority website](https://www.pa.org.mt/pacasedetails?CaseType=PA/07552/24)

[Plans, case officer report and decision on eapps](https://eapps.pa.org.mt/Case/CaseDetails?caseType=PA&casenumber=07552&caseYear=24)

## Planning activity around Site at (Field), Gebel Sarnu, San Pawl il-Bahar

No other applications recorded nearby yet.

Approval estimate for new construction applications like this here: about 93% (likely range 63–100%, low reliability, from 0 comparable decisions nearby). Outside the development zone, where approvals are harder. Indicative only. It's based on decisions for similar nearby applications, not on the drawings or the case officer's report; it gets better as documents are added from eapps.

## More by Julian Borg

- [**PA/07521/26** Siggiewi](https://propertylist.mt/permit/PA-07521-26/siggiewi-demolition-of-existing-dwelling-and-proposed-construction): Demolition of existing dwelling and proposed construction of basement garage, child-care at ground floor (Class 2C) and one apartment at first floor, one… Pending, validated 28 October 2026, 4 floors plus a receded floor
- [**PA/07491/26** Zebbug](https://propertylist.mt/permit/PA-07491-26/zebbug-demolition-of-existing-terraced-house): Proposed demolition of existing terraced house, excavation of basement and proposed construction of basement garages, ground floor maisonette, apartment at… Pending, validated 28 October 2026, 4 floors plus a receded floor
- [**PA/07351/26** Siggiewi](https://propertylist.mt/permit/PA-07351-26/siggiewi-sanction-minor-internal-changes-to-garage-from): To sanction minor internal changes to garage from that approved in PAPB/1285/87. Pending
- [**PA/07293/26** Siggiewi](https://propertylist.mt/permit/PA-07293-26/siggiewi-sanction-minor-changes-from-the-approved-permit): To sanction minor changes from the approved permit PAPB/2138/92, proposed alterations at ground and first floor level including the subdivision of existing… Pending, validated 21 October 2026
- [**PA/07191/26** Zebbug](https://propertylist.mt/permit/PA-07191-26/zebbug-alterations-at-ground-floor): Alterations at ground floor, demolition of first and washroom and the proposed construction of 2 units and first floor, 2 units at second floor, 2 units at… Pending, validated 21 October 2026, 4 floors plus a receded floor
- [**PA/06767/26** Siggiewi](https://propertylist.mt/permit/PA-06767-26/siggiewi-demolition-of-existing-terraced-house): Proposed demolition of existing terraced house, excavation of basement garage and construction of ground floor maisonette, apartment on each level at first… Pending, validated 7 October 2026, 4 floors plus a receded floor

[All applications by Julian Borg](https://propertylist.mt/perit/julian-borg)

[All planning applications in San Pawl il-Bahar](https://propertylist.mt/planning-applications/san-pawl-il-bahar)