PA/01314/23: conversion of two debilitated buildings to a in Floriana

26,28,30, Triq il-Kapuccini c/w 89,90,91,93, Triq San Tumas, Floriana

Proposed conversion of two debilitated buildings to a guesthouse (Class 3A) including ancillary facilities and splash pool on roof. Works include internal alterations, demolition of dangerous structures, reconstruction of roofs in different levels, and two additional floors on part of the site. Proposed A4 size sign.

Status
Granted (This application has been approved by Planning Board / Commission.)
Location
26,28,30, Triq il-Kapuccini c/w 89,90,91,93, Triq San Tumas, Floriana
Locality
Floriana
Applicant
St. Ursula Ltd Attn: George Briffa
Perit
Perit Carmel Farrugia
Application type
Full development permission
Zone
Within Development Zone
Type of works
Hotel
Received
3 October 2022
Validated
8 March 2023
Published
8 March 2023
Comments close
14 April 2023
Recommendation
Grant Permission
Decision
Grant Permission
Decision date
31 January 2024
Permit expires
14 February 2029

Case details on the Planning Authority website

Plans, case officer report and decision on eapps

Planning activity around 26,28,30, Triq il-Kapuccini c/w 89,90,91,93, Triq San Tumas, Floriana

150 other applications within 300 m: 93 granted, 3 refused, 22 pending. 97% of decided applications nearby were granted. Tallest granted nearby: 6 floors (PA/02172/22).

On Triq il-Kapuccini: 15 other applications, 11 granted and 0 refused.