PA/03128/23: Sanctioning of variations to PA/05584/19 which include in San Pawl il-Bahar
91, Triq San Publju, San Pawl il-Bahar
Sanctioning of variations to PA/05584/19 which include minor displacements of internal and external walls, and apertures. Proposed travertine cladding on the façade.
- Status
- Granted (This application has been approved by Planning Board / Commission.)
- Location
- 91, Triq San Publju, San Pawl il-Bahar
- Locality
- San Pawl il-Bahar
- Applicant
- George Fenech
- Perit
- MASStudio
- Application type
- Full development permission
- Zone
- Within Development Zone
- Type of works
- Sanctioning
- Received
- 4 April 2023
- Validated
- 31 May 2023
- Published
- 31 May 2023
- Comments close
- 30 June 2023
- Recommendation
- Grant Permission
- Decision
- Grant Permission
- Decision date
- 15 November 2023
- Permit expires
- 29 November 2028
Case details on the Planning Authority website
Plans, case officer report and decision on eapps
Planning activity around 91, Triq San Publju, San Pawl il-Bahar
7 other applications on the same street: 5 granted, 0 refused, 1 pending. 100% of decided applications nearby were granted.
On Triq San Publju: 7 other applications, 5 granted and 0 refused. Periti active on this street: CVC Architecture, Daniel Grima.
Approval estimate for sanctioning applications like this here: about 95% (likely range 65–100%, low reliability, from 2 comparable decisions nearby). Indicative only. It's based on decisions for similar nearby applications, not on the drawings or the case officer's report; it gets better as documents are added from eapps.
- PA/01085/26 San Pawl il-Bahar: To demolish existing penthouse and construct two additional two bedroom apartments and a one bedroom penthouse on top.
- PA/07450/25 San Pawl il-Bahar: To convert washroom to a domestic store at fourth floor level. Sanctioning of drying area at fifth floor level and proposed conversion of the latter to a…
- PA/05893/24 San Pawl il-Bahar: Construction of washroom between two existing structures at roof level including opening of doorway in common parts.
- PA/03651/24 San Pawl il-Bahar: Extension at roof level and alterations at ground and lower roof floor level.
- PA/07720/23 San Pawl il-Bahar: Sanctioning to correct approved section and rear façade in PA/5550/09, lowering of sills on rear façade and re-opening of blocked up windows on the façade.
- PA/00324/21 San Pawl il-Bahar: Proposed triplex dwelling overlying block of apartments.
- PA/07146/26 San Pawl il-Bahar: To construct a 1-bedroom apartment at first floor level.
More by MASStudio
- PA/07770/26 Swieqi: Sanctioning of differences from approved PA/02840/92, in Garage No 5.
- PA/07724/26 Balzan: Change of use of a pre-1967 domestic garage to a studio maisonette.
- PA/07658/26 St Julians: Proposed change of use from approved 30 rooms Class 3A guesthouse (PA/02543/25) to 39 rooms Class 3B 3-star hotel while keeping the same approved volume and…
- PA/06521/26 Santa Venera: Sanctioning of minor changes from approved PA/07822/06 of third floor level. And proposed extension of the existing apartment at third-floor level and…
- PA/06435/26 Rabat: Demolition of existing property and construction of ground floor maisonette, two overlying apartments at first and second floor, and a duplex unit at third…
- PA/06423/26 Swieqi: Proposed demolition of existing property and reconstruction of basement garages and residential units, amalgamated with the adjacent property already covered…
More from George Fenech
- PA/06102/26 Msida: To sanction discrepancies in plan from approved plans (PA2993/24).
- PA/03541/26 Qormi: Sanctioning of garage as built and propose change of use from existing garage to Class 4B shop and including proposed signage on facade.
- PA/02741/26 San Pawl il-Bahar: To demolish existing dwellings and to excavate basement floors. To construct garages basement floor levels. To construct a Class 4D restaurant at ground floor…
- PA/07284/25 Munxar: Change of use from street level garage to Class 4A.
- PA/06805/25 San Pawl il-Bahar: Proposed demolition of existing penthouse and construction of 3 bedroom apartment at fourth floor and one bedroom penthouse at receded fifth floor.
- PA/05980/25 Rabat: To sanction departures to dwelling from PA/3741/19 which includes correction of the site configuration and changes to the internal layout, room uses, site…