PA/03525/26: demolition of building and excavation of site in Sliema

Canopy by Hilton, Triq it-Torri c/w Triq L. Graham c/w, Triq Milner, Sliema

Proposed demolition of building and excavation of site (Phase 3 to hotel development). Phase 4 for construction to be covered by separate permit.

Status
Suspended (Application processing is currently suspended at the perit's request)
Location
Canopy by Hilton, Triq it-Torri c/w Triq L. Graham c/w, Triq Milner, Sliema
Locality
Sliema
Applicant
Preluna Ltd Attn: Joseph Andres Preca
Perit
Perit Michael Anastasi
Application type
Full development permission
Zone
Within Development Zone
Type of works
Demolition & New Construction
Received
9 February 2026
Validated
3 June 2026
Published
3 June 2026
Comments close
3 July 2026

Case details on the Planning Authority website

Plans, case officer report and decision on eapps

Planning activity around Canopy by Hilton, Triq it-Torri c/w Triq L. Graham c/w, Triq Milner, Sliema

187 other applications within 300 m: 105 granted, 9 refused, 18 pending. 92% of decided applications nearby were granted. Tallest granted nearby: 15 floors (PA/07209/23).

On Triq it-Torri: 141 other applications, 75 granted and 7 refused; granted buildings are typically 8 floors, the tallest 15. Periti active on this street: Edwin Mintoff, David Vassallo, Paul Camilleri, Malcolm Xuereb, Christian Spiteri.

Approval estimate for demolition & new construction applications like this here: about 93% (likely range 63–100%, low reliability, from 11 comparable decisions nearby). Indicative only. It's based on decisions for similar nearby applications, not on the drawings or the case officer's report; it gets better as documents are added from eapps.