propertylist

PA/05804/23: propose roofing over terrace of existing penthouse in San Pawl il-Bahar

Berkely Court, Apt 9, Triq it-Turisti, San Pawl il-Bahar

To propose roofing over terrace of existing penthouse, extension to facade and to construct two penthouses on the overlying floor .

Status
Granted (This application has been approved by Planning Board / Commission.)
Location
Berkely Court, Apt 9, Triq it-Turisti, San Pawl il-Bahar
Locality
San Pawl il-Bahar
Applicant
Andrew Gauci
Perit
Perit Mark Caruana
Application type
Full development permission
Zone
Within Development Zone
Type of works
New Construction (Residential)
Height
1 floor plus a receded floor
Residential units
2
Received
26 May 2023
Validated
11 October 2023
Published
11 October 2023
Comments close
10 November 2023
Recommendation
Grant Permission
Decision
Grant Permission
Decision date
26 November 2024
Permit expires
11 December 2029

Case details on the Planning Authority website

Plans, case officer report and decision on eapps

Planning activity around Berkely Court, Apt 9, Triq it-Turisti, San Pawl il-Bahar

174 other applications within 300 m: 100 granted, 4 refused, 21 pending. 96% of decided applications nearby were granted. Tallest granted nearby: 7 floors (PA/00272/26).

On Triq it-Turisti: 63 other applications, 36 granted and 2 refused; granted buildings are typically 7 floors, the tallest 7. Periti active on this street: Wayne Scerri, Colin Zammit, Matthew Gauci, Gilbert Bartolo, David Psaila.

Approval estimate for new construction applications like this here: about 94% (likely range 64–100%, low reliability, from 6 comparable decisions nearby). Indicative only. It's based on decisions for similar nearby applications, not on the drawings or the case officer's report; it gets better as documents are added from eapps.

More by Mark Caruana

All applications by Mark Caruana

More from Andrew Gauci

All planning applications in San Pawl il-Bahar