PA/07112/24: sanction apartment as built in San Pawl il-Bahar
No. 10, Flt 1 & Garage, San Marino Building, Sqaq tax-Xama', San Pawl il-Bahar
To sanction apartment as built, in view of original permit not being traced. Proposed subdivision of unit into two, the latter involves alterations to the same unit.
- Status
- Granted (This application has been approved by Planning Board / Commission.)
- Location
- No. 10, Flt 1 & Garage, San Marino Building, Sqaq tax-Xama', San Pawl il-Bahar
- Locality
- San Pawl il-Bahar
- Applicant
- Enrique Mizzi
- Perit
- Perit Wayne Scerri
- Application type
- Full development permission
- Zone
- Within Development Zone
- Type of works
- Sanctioning
- Received
- 20 September 2024
- Validated
- 16 October 2024
- Published
- 16 October 2024
- Comments close
- 15 November 2024
- Recommendation
- Refuse Permission
- Decision
- Grant Permission
- Decision date
- 11 April 2025
- Permit expires
- 23 April 2030
Case details on the Planning Authority website
Plans, case officer report and decision on eapps
Planning activity around No. 10, Flt 1 & Garage, San Marino Building, Sqaq tax-Xama', San Pawl il-Bahar
43 other applications within 300 m: 27 granted, 1 refused, 5 pending. 96% of decided applications nearby were granted. Tallest granted nearby: 7 floors (PA/02082/24).
On Sqaq tax-Xama': 6 other applications, 2 granted and 0 refused; granted buildings are typically 3 floors, the tallest 3. Periti active on this street: Ruben Sciortino, Daniel Grima.
Approval estimate for sanctioning applications like this here: about 95% (likely range 65–100%, low reliability, from 8 comparable decisions nearby). Indicative only. It's based on decisions for similar nearby applications, not on the drawings or the case officer's report; it gets better as documents are added from eapps.
- PA/02610/26 San Pawl il-Bahar: Proposal includes the demolishing of the existing stairs, construction of new stairs and access ramp at Bajja tax-Xama'.
- PA/03263/25 San Pawl il-Bahar: Proposed additional apartment at fifth floor level to that approved in PA/03805/15. Development will now consist of a total of 3 garages, 1 shop (Class 4B), 5…
- PA/08108/25 San Pawl il-Bahar: Minor internal and external alterations to existing dwelling including the installation of a lift and an addition of a receded third floor structure.
- PA/03547/21 San Pawl il-Bahar: To demolish 2 residences (residences do not have garages) and construct ground garages and overlying residential units.
- PA/02770/21 San Pawl il-Bahar: Minor internal alterations
- PA/06217/25 San Pawl il-Bahar: Alterations to PA 2677/10 including extension of top apartment.
- PA/03128/23 San Pawl il-Bahar: Sanctioning of variations to PA/05584/19 which include minor displacements of internal and external walls, and apertures. Proposed travertine cladding on the…
- PA/00250/25 San Pawl il-Bahar: Demolition of existing dwelling and construction of Class 4B shop (1 unit) and overlying dwelling (1 unit on 5 levels) and fixing of sign.
- PA/04883/23 San Pawl il-Bahar: Renewal of PA4664/18 - To make alterations to existing setback floor including roofing over of existing terrace and construct a new overlying setback floor.
- PA/05934/23 San Pawl il-Bahar: To sanction the addition of a backyard to an approved Class 4B shop at semi-basement plan and to correct drafting error of back-yard at semi-basement level…
- PA/00915/20 San Pawl il-Bahar: To sanction changes to garage facade including the opening of a window.
- PA/07146/23 San Pawl il-Bahar: To split triplex penthouse - approved in PA4664/18 - into three separate apartments.
- PA/07146/26 San Pawl il-Bahar: To construct a 1-bedroom apartment at first floor level.
- PA/05893/24 San Pawl il-Bahar: Construction of washroom between two existing structures at roof level including opening of doorway in common parts.
- PA/03651/24 San Pawl il-Bahar: Extension at roof level and alterations at ground and lower roof floor level.
More by Wayne Scerri
- PA/07358/26 Sliema: To demolish existing internal walls and ceilings (retaining facade), plus construction of a Class 3A guest house at ground, first, second, third and setback…
- PA/07337/26 Nadur: Proposed internal alterations to approved PA6882/22.
- PA/07302/26 Kercem: To retain facade, to partly internal additions to existing pre-1967 dwelling, to excavate and to construct 3 residential dwellings. To also carry out…
- PA/07245/26 Kercem: To demolish existing building, propose excavation and construction of reservoir, 9 garages at basement level, office Class 4A, signage, residential units at…
- PA/07175/26 Kalkara: To extend the existing washroom at setback floor level, in an existing pre-1968 dwelling.
- PA/07021/26 St Julians: To convert an existing dilipadited pre-67 residential structure on the same built up footprint consisting of internal and external modifications including…
All applications by Wayne Scerri
More from Enrique Mizzi
- PA/05355/26 San Pawl il-Bahar: To sanction apartment as built, and propose change of color of facade and apertures.
- PA/06321/25 San Pawl il-Bahar: Proposed window openings.
- PA/03405/24 San Pawl il-Bahar: To sanction apartment and garage as built, in view of original permit not being traced.
- PA/00157/24 Swieqi: Sanctioning of alteration to permit number PA/01831/23. The following includes change in wall configuration, opening types, use of rooms and alteration to…
- PA/01831/23 Swieqi: Proposed alterations to existing pre-2015 unit including additional overlying two units, one of which a duplex unit located at third and recessed floor level.…