PA/01082/24: demolish the existing house in San Pawl il-Bahar
116/114, My Rest, Triq J. Quintinus, Bugibba, San Pawl il-Bahar
To demolish the existing house, excavate one floor together with the reservoir and to construct a maisonette and 12 apartments and 1 penthouse.
- Status
- Granted (This application has been approved by Planning Board / Commission.)
- Location
- 116/114, My Rest, Triq J. Quintinus, Bugibba, San Pawl il-Bahar
- Locality
- San Pawl il-Bahar
- Applicant
- Raymanda Ltd Attn: Emanuel Vella
- Perit
- Perit Silvienne Camilleri
- Application type
- Full development permission
- Zone
- Within Development Zone
- Type of works
- Demolition & New Construction (Residential)
- Residential units
- 14
- Received
- 3 June 2023
- Validated
- 28 February 2024
- Published
- 28 February 2024
- Comments close
- 5 April 2024
- Recommendation
- Grant Permission
- Decision
- Grant Permission
- Decision date
- 1 April 2025
- Permit expires
- 16 April 2030
Case details on the Planning Authority website
Plans, case officer report and decision on eapps
Planning activity around 116/114, My Rest, Triq J. Quintinus, Bugibba, San Pawl il-Bahar
157 other applications within 300 m: 93 granted, 5 refused, 19 pending. 95% of decided applications nearby were granted. Tallest granted nearby: 8 floors (PA/08169/25).
On Triq J. Quintinus: 21 other applications, 12 granted and 0 refused; granted buildings are typically 6 floors, the tallest 8. Periti active on this street: David Mifsud Parker, Samuel Formosa.
Approval estimate for demolition & new construction applications like this here: about 95% (likely range 65–100%, low reliability, from 4 comparable decisions nearby). Indicative only. It's based on decisions for similar nearby applications, not on the drawings or the case officer's report; it gets better as documents are added from eapps.
- PA/01660/23 San Pawl il-Bahar: Change of use from greengrocer approved in PA7432/03 to Class 4C outlet.
- PA/05797/23 San Pawl il-Bahar: To sanction minor internal alterations at second floor to the approved PA/03952/99.
- PA/08169/25 San Pawl il-Bahar: Proposed alterations to property, part already approved by virtue of PA/11078/17; and construction of new unit at seventh floor level with a different layout…
- PA/01199/25 San Pawl il-Bahar: To sanction internal and external variations from PA6255/06.
- PA/02922/21 San Pawl il-Bahar: Conversion of 1no. penthouse (originally approved by PA/7434/06 into 1no. apartment at fifth floor level and construct 1no. apartment at receded floor level.…
- PA/00396/24 San Pawl il-Bahar: Proposed construction of additional residential unit at receded sixth floor level, and alterations to existing common area.
- PA/05505/24 San Pawl il-Bahar: Change of use from greengrocer approved in PA7432/03 to Class 4B outlet as per LN74 of 2014.
- PA/04951/26 San Pawl il-Bahar: Proposed roofing of the front garden area with a temporary lightweight glass and steel canopy, and installation of new signage on the upper part of the…
- PA/04782/24 San Pawl il-Bahar: Proposed demolition of existing terrace house, excavation of 1 level basement housing, 8 private parking car spaces, and construction of 15 dwellings from…
- PA/03153/22 San Pawl il-Bahar: To sanction internal and external alterations from approved permit PA3787/99 including removal, addition and shifting of walls at second floor level and…
- PA/04408/26 San Pawl il-Bahar: Change of use from private car garage to a public service garage.
- PA/02650/21 San Pawl il-Bahar: To install canopy in front garden, in connection to Class 4B retail outlet (PA/02113/19)
- PA/00049/21 San Pawl il-Bahar: Change of use from garage to Class 4B Shop.
- PA/02274/26 San Pawl il-Bahar: Proposed sanctioning of variations to garage from approved permit PA/05947/09. Proposed changes to facade.
- PA/07956/24 San Pawl il-Bahar: To sanction garage as built (plotting sheets not traced), and to propose change of use from garage to Class 4D snack-bar.
More by Silvienne Camilleri
- PA/07766/26 St Julians: To sanction difference from PA/01477/14 on first floor level in Triq Gorg Borg Oliver / Triq il-Kbira, St Julian’s
- PA/07236/26 Dingli: To sanction differences from PA/05569/09. To proposed a vehicular entrance, to provide a ramp in the garden from the pavement to the garden level. and to…
- PA/07140/26 Naxxar: To excavate and construct a basement level with 11 spaces for industrial use (Class 5B), to construct a ground floor level with 10 spaces for industrial use…
- PA/06573/26 Dingli: To remove garage at basement level as approved in PA/03405/22 and to replace the garage at ground floor level with a residential unit (Class 1) and to propose…
- PA/06245/26 Naxxar: To excavate two basement levels and to construct a total of 29 spaces of Industrial (Class 5B), 49 spaces of warehousing (Class 6A) and 30 parking spaces.
- PA/06004/26 Qrendi: To sanction the drawings from PA/03164/25, to demolish some ceilings and re build them. To construct a bedroom and a laundry room. To excavate and to…
All applications by Silvienne Camilleri
More from Raymanda Ltd
- PA/00829/26 San Pawl il-Bahar: To propose changes from PA/01082/24, to change the ground floor from Class 1 to Class 2C and to construct a pool at roof level.
- PA/03480/25 San Gwann: Change of use of Class 4A office block as approved in PA/07340/22 to a Class 3A guesthouse with 11 guest rooms and ancillary facilities including a Class 4C…
- PA/00874/24 Qormi: Proposed demolition of existing building and proposed construction of apartment block with 2 maisonettes, 8 apartments and 1 penthouse, with underlying…
- PA/04840/23 Iklin: Proposed demolition of existing dwelling and construction of apartment block with 3 apartments and 1 penthouse, underlying Class 4B unit and a basement…