PA/02732/23: demolish an existing structure including the garage in San Pawl il-Bahar
60 and 62, Triq Sir Luigi Preziosi, San Pawl il-Bahar
To demolish an existing structure including the garage and to re-construct garage and construction of a shop Class 4B at ground floor with overlying 6 residential apartments from first to seventh (receded) floor as already approved in PA6332/17.
- Status
- Granted (This application has been approved by Planning Board / Commission.)
- Location
- 60 and 62, Triq Sir Luigi Preziosi, San Pawl il-Bahar
- Locality
- San Pawl il-Bahar
- Applicant
- Mr Neville Galea
- Perit
- Perit Mark Camilleri
- Application type
- Full development permission
- Zone
- Within Development Zone
- Type of works
- Demolition & New Construction (Residential)
- Height
- 7 floors
- Residential units
- 6
- Received
- 8 March 2023
- Validated
- 17 May 2023
- Published
- 17 May 2023
- Comments close
- 16 June 2023
- Recommendation
- Grant Permission
- Decision
- Grant Permission
- Decision date
- 18 July 2023
- Permit expires
- 2 August 2028
Case details on the Planning Authority website
Plans, case officer report and decision on eapps
Planning activity around 60 and 62, Triq Sir Luigi Preziosi, San Pawl il-Bahar
26 other applications on the same street: 17 granted, 2 refused, 4 pending. 89% of decided applications nearby were granted. Tallest granted nearby: 8 floors (PA/07562/24).
On Triq Sir Luigi Preziosi: 26 other applications, 17 granted and 2 refused; granted buildings are typically 7 floors, the tallest 8. Periti active on this street: Fabrizio Baldacchino, Aquilina and Sammut Alessi, Stephen Farrugia, Kurt Camilleri Burlo', Martin Farrugia.
Approval estimate for demolition & new construction applications like this here: about 95% (likely range 65–100%, low reliability, from 4 comparable decisions nearby). Indicative only. It's based on decisions for similar nearby applications, not on the drawings or the case officer's report; it gets better as documents are added from eapps.
- PA/06988/26 San Pawl il-Bahar: Demolition of existing first floor property and proposed construction of 6 overlying units.
- PA/05933/26 San Pawl il-Bahar: Sanctioning of Flat 3 as built due to deviations from PB/05377/85. Deviations consist of shifting of facade apertures, internal shifting of walls and updating…
- PA/07059/26 San Pawl il-Bahar: Proposed change of use from remaining part of garage to garage for public service garage. No changes to front elevation. One private car is being retained.
- PA/06011/26 San Pawl il-Bahar: To propose additional bedroom and bathroom.
- PA/02528/26 San Pawl il-Bahar: To sanction changes to parking layout at level 0 and internal alterations at level 7 and to propose pool at roof level.
- PA/02191/26 San Pawl il-Bahar: Proposed change of use from 1-bedroom duplex apartment at ground floor to a class 4B shop at ground floor and a 1-bedroom apartment at 1st floor. This…
- PA/02074/26 San Pawl il-Bahar: Construction of 1 x 2-bedroom flat and 1 x 1 bedroom penthouse over existing block of flats and variation from the official alignment.
- PA/05154/25 San Pawl il-Bahar: Construction of staircase from receded to roof floor levels and construction of pool and planter at roof level.
- PA/05468/25 San Pawl il-Bahar: Sanctioning of two garages at street level and Sanctioning of garages previously approved as storage space in permit PB434/90. Proposed change of use from 2…
- PA/04654/25 San Pawl il-Bahar: Proposed sanctioning of small extension at first and second floor level to pre-67 dwelling, and proposed raising of party wall in back yard for privacy.
- PA/04826/25 San Pawl il-Bahar: Construction of 1 x 2-bedroom flat and 1 x 1 bedroom penthouse over existing block of flats.
- PA/01924/25 San Pawl il-Bahar: To sanction variations to PA/00333/17 and correction of site.
- PA/00528/25 San Pawl il-Bahar: Renewal of PA/07445/19 - Alterations and additions to existing duplex at 3rd and 4th floor and construction of 1 bedroom duplex at 5th and 6th floor.
- PA/07562/24 San Pawl il-Bahar: To demolish existing apartment block and construct a 7 floor +1 receded unit residential block overlying ground floor garages and excavate a small basement…
- PA/04982/24 San Pawl il-Bahar: To demolish existing staircase and propose construction of new stairs and lift and additional two apartments at fourth and fifth floors and one duplex unit at…
More by Mark Camilleri
- PA/07824/26 Marsaskala: To carry out alterations to approved (PA 230/23) basement garage level due to retaining the 0.75m from the party wall, converting of approved ground floor…
- PA/07556/26 Zejtun: To sanction residential dwelling from approved PB3973/79 and to propose internal structural alterations and extension at setback floor level.The application…
- PA/07516/26 Luqa: Partial change of use to Y-plate garage.
- PA/07394/26 Zejtun: To demolish existing disused farm (Class 7) and excavate and build underground reservoir and parking spaces, overlying old people's home and ancillary…
- PA/07392/26 Kalkara: Correction of site from as approved by PA3787/06 and placing of solar panels and cement board screening to existing townhouse (over existing washroom).
- PA/07268/26 Rabat: To sanction the existing rubble wall and franka wall exceeding 1.2 metres in height, and to propose the construction of a sheep farm with ancillary…
All applications by Mark Camilleri
More from Neville Galea
- PA/08340/25 San Pawl il-Bahar: To convert the existing penthouse into two penthouses. To consider car parking within the same block as per approved building permit PA/00614/19.
- PA/05866/25 Balzan: Internal amendments to existing ground floor plan including the addition of a ground floor garage, demolition of washroom at first floor level and the…
- PA/05440/25 Qormi: Demolition of existing derelict structures and proposed excavation to accommodate one level of construction of five garages at basement level and a reservoir…
- PA/03874/25 San Pawl il-Bahar: Conversion of an approved duplex in PA7232/17 into two one-bedroom units.
- PA/02293/24 Naxxar: To demolish existing residential unit and construct 2 garages at level 0, 4 apartments at levels 1-4 plus overlying penthouse at level 5.
- PA/02719/23 San Pawl il-Bahar: Placing tables and chairs in front of an approved Class 3B hotel and Class 4D restaurant over a wooden demountable platform cordoned with safety bollards on…