PA/05662/23: repair part of the deteriorated concrete wall in Siggiewi
Site at, Slipway, Ghar Lapsi, Siggiewi
To repair part of the deteriorated concrete wall and extend the same wall to provide better shelter to the slipway.
- Status
- Granted (This application has been approved by Planning Board / Commission.)
- Location
- Site at, Slipway, Ghar Lapsi, Siggiewi
- Locality
- Siggiewi
- Applicant
- Stephen Bonello
- Perit
- Perit Mario Ellul
- Application type
- Full development permission
- Zone
- Outside Development Zone
- Type of works
- Other
- Received
- 20 July 2023
- Validated
- 27 September 2023
- Published
- 27 September 2023
- Comments close
- 27 October 2023
- Recommendation
- Grant Permission
- Decision
- Grant Permission
- Decision date
- 1 December 2023
- Permit expires
- 12 December 2028
Case details on the Planning Authority website
Plans, case officer report and decision on eapps
Planning activity around Site at, Slipway, Ghar Lapsi, Siggiewi
No other applications recorded nearby yet.
Approval estimate for other applications like this here: about 95% (likely range 65–100%, low reliability, from 0 comparable decisions nearby). Outside the development zone, where approvals are harder. Indicative only. It's based on decisions for similar nearby applications, not on the drawings or the case officer's report; it gets better as documents are added from eapps.
More by Mario Ellul
- PA/05806/24 Birzebbuga: Reconstruction, extension and improvement of existing concrete footpath along the coast for better access to the rocky coast and to the public pathway around…
- PA/05472/24 Qrendi: Refurbishment works at the quay of Wied iz-Zurrieq and surrounding areas. Redevelopment of ticket booth for Blue Grotto operators. Construction of public…
- PA/02780/24 Marsaskala: Excavation and construction of a silt pit for the temporary deposition of liquid silt during the cleaning operations of Zabbar stormwater tunnel. Works entail…
- PA/07297/23 Marsa: Construction of an electricity substation, main electrical switch room and backup generator for the new sports complex Class 3C approved in PA5600/19.
- PA/00779/23 Mellieha: Demolishing of existing concrete stairs and construction of an access for all ramp to pre-1968 boathouses.
- PA/03156/22 Siggiewi: Coastal protection works at Ghar Lapsi (East Cove) consisting in the shifting of rock boulders from quay and seabed to protect the toe of the cliff to reduce…
All applications by Mario Ellul
More from Stephen Bonello
- PA/06636/26 Santa Venera: To sanction changes to the approved garage (PA/6953/06) and the proposed extension of existing storage rooms.
- PA/06497/25 Paola: Proposed dismantling of existing deteriorated steel canopy and construction of new canopy in same material and structural design.
- PA/03677/24 Paola: The proposal involves transforming a section of the former Pace Grasso / Schreiber Stadium into a public park, which includes the enhancing and widening of…
- PA/05407/23 Sliema: Renewal of PA1496/18: Renewal of PA2459/12 - Proposed regeneration works at Part of Triq ix-Xatt. Proposal to include removal of existing parking landscape…
- PA/01556/23 Rabat: Proposed internal and external changes in office building, demolition and reconstruction of garage and security area, addition of rubble wall in certain…
- PA/00767/23 Pembroke: Internal alterations, refurbishment works, installation of pv panels on roof and replacement of roof.